amazon-flexiscreen-hero-image

Amazon/Uplands Retail Enfield, UK

Flexiscreen keeps the parcels moving during upgrades at a major Amazon logistics station

Customer

Amazon/Uplands Retail

Sector

Warehousing and Logistics

Location

Enfield, UK

Solution

Flexiscreen

Protecting logistics operations from weather ingress

When Amazon replaced dock doors at its DIG1 delivery station in Enfield, the site had to continue operating at full capacity.

Westgate Global’s Flexiscreen kept the site weather-tight and fully operational. Hung at an angle from the existing building frame, with no supporting structure required, it was delivered and fitted within three weeks.

amazon-a

Upgrades without downtime 

DIG1, in Brimsdown, Enfield, is one of Amazon’s delivery stations, the final link in its logistics chain. Parcels arrive from Amazon’s fulfilment and sortation centres, are sorted by route, and are loaded onto vans for customers across north London and beyond. When Amazon upgraded the station’s dock doors, the works had to be completed without slowing this critical step in the logistics giant’s operations. 

An entire external wall had to come out, leaving a 45 metre-wide opening. Contractors needed to work from outside while operations continued inside, so both sides of the opening had to stay accessible. With the building being 14 metres high – and a weather-tight seal required –  the opening was too tall for a practical scaffold frame, and any structure inside would have sat across the trolley route and disrupted parcel flow.

The protection also had to be designed, made and installed quickly to keep pace with the dock-door programme.

Flexiscreen® protects operations from weather ingress

Working alongside main contractor Uplands Retail, the Westgate Global team carried out a full site survey and recommended Flexiscreen, an engineered temporary weather-protection and dust screen.

Constructed from polyester-reinforced, fire-retardant fabric with PVC coating, Flexiscreen shielded the open building from the weather, regulated the internal temperature, and stopped construction dust from spreading into the live parcel sorting areas.

At DIG1, the deciding factor was Flexiscreen’s suspended, frameless design. The screen was hung from the building’s existing structure using clips and S-hooks, so no steel framework or scaffold was needed, and the trolley route stayed completely clear.

Because Flexiscreen can be installed at an angle, the panels were fixed to the existing building framework in a way that worked around both the opening and the operational space. It is a proven approach: on an earlier refurbishment for Birds Eye, Flexiscreen was chosen partly because it can be fitted at an angle, a clear advantage over conventional solutions.

The screen was designed to cover the full 14 metre by 45 metre opening, with roll-up sections built in for vehicle and equipment access. Once in place, its V-overlap panel connections formed an over-99% air and dust-tight seal, keeping the weather out and conditions stable inside for staff and parcels.

Manufactured in the UK and quick to install, the screen was delivered and fitted within three weeks of the initial enquiry. 

Construction work completed without disruption 

DIG1 stayed fully operational throughout the wall removal and dock-door installation. With no frame or scaffold on the operational floor, the trolley route stayed clear, and parcels kept moving as normal.

Contractors kept access to both sides of the works, and the open elevation was protected from the weather across its full height. For a busy and growing station like DIG1, that meant the new dock doors went in without interrupting deliveries to customers.

"Taking out a 45-metre wall on a live delivery station could easily interrupt operations. For an operation like Amazon, which manages huge volumes and incredibly tight delivery windows, things had to keep moving. Scaffold wasn't an option at that height, and anything on the floor would have blocked the trolley route. Flexiscreen hangs from the building's own frame, so we could seal the opening, keep both sides accessible and let Amazon carry on as normal, with no downtime."
Zander Thomas External Sales Manager, Westgate Global